EDF : Flamanville EPR: status update
Press Release21 January 2019 Flamanville EPR: status update EDF actively continues to implement the action plan on welds of the main secondary system announced on 25 July 2018. The "hot tests" are now scheduled to commence during the second half of February...
London,
(informazione.news - comunicati stampa - energia)
EDF actively continues to implement the action plan on welds of the main secondary system announced on 25 July 2018. The "hot tests" are now scheduled to commence during the second half of February.
The teams of EDF and of its industrial partners remain fully mobilized to complete the loading of nuclear fuel during the 4 quarter of 2019 under target construction costs for EDF at the commissioning date kept at €10.9 billion .
Per maggiori informazioni
Ufficio Stampa
Nasdaq GlobeNewswire (Leggi tutti i comunicati)
2321 Rosecrans Avenue. Suite 2200
90245 El Segundo Stati Uniti
2321 Rosecrans Avenue. Suite 2200
90245 El Segundo Stati Uniti
Allegati
Non disponibili