Udokan Copper Completes Installation of Coarse Ore Crusher
All processing parameters of the coarse crushing plant are controlled and adjusted from the automated operator's workplace, with real-time controlling possible.
Once mining at the Udokan MMP starts, the ore will be transported to the coarse crushing plant by 130-tonne dumper trucks.
After the coarse crushing, the ore will go to the storage and then to the beneficiation plant through the crushing and conveyor unit consisting of two mainline belts with total length of 2.8 km.
Construction works are in full swing throughout the crushing and conveyor unit. In particular, the foundation and steel structures of Conveyor #1 Gallery are installed. Steel structures are also being installed for the transfer unit from Conveyor #1 to Conveyor #5. Along the Conveyor #5 route, the foundation of the horizontal section is already installed and the conveyor is being assembled. The installation of steel structures for the Conveyor #5 tension station, ore storage, fine crushing plant, and conveyor galleries between the ore storage and the beneficiation plant is close to completion. The underground part of the ore storage sees the installation of ore feeding conveyors from the ore storage to the main building of the beneficiation plant.